Get the objective questions and solutions from the MSc Construction Project Management Entrance Examination 2080 at Far Western University. Includes s
Far Western University, Faculty of Engineering, MSc CPM Entrance Examination 2080.
This is the entrance examination paper, time is 2 hours and full marks is 100. Each question carries 1 mark.
Subject: Construction Project Management
Objective questions with their solutions asked in the MSc CPM Entrance Examination 2080.
A) 24
B) 40
C) 96
D) 150
Answer: A
A) 21%
B) 42%
C) 84%
D) 96%
Answer: C
A) 1.5
B) 2.5
C) 3
D) 4
Answer: B
A) 24,025 mm²
B) 22,725 mm²
C) 24,000 mm²
D) 24,075 mm²
Answer: A
A) 6
B) 9
C) 15
D) 24
Answer: B
A) 16
B) 64
C) 96
D) 128
Answer: C
A) 40º
B) 50º
C) 60º
D) 70º
Answer: D
A) 4
B) 3
C) 2
D) 1
Answer: A
A) 20
B) 40
C) 60
D) 80
Answer: D
A) 2π
B) π
C) π2
D) √π
Answer: A
A) b⁄a = 2
B) a⁄b = 2
C) a = b
D) a = -b
Answer: B
A) l2+m2−n2=0
B) lmn=1
C) l2+m2+n2=1
D) l2m2+n2=1
Answer: C
A) Circle
B) Straight line
C) Parabola
D) None of these
Answer: B
A) 40%
B) 35%
C) 30%
D) 25%
Answer: A
A) ycosx=sinx+c
B) ysinx=cosx+c
C) ysinx=sinx+c
D) ycosx=−sinx+c
Answer: B
A) 40
B) 48
C) 60
D) 64
Answer: C
A) 50
B) 100
C) 150
D) 200
Answer: B
A) [d−b−ca]
B) [−dbc−a]
C) [acbd]
D) [−a−b−c−d]
Answer: A
A) 6
B) 2/3
C) 4/3
D) 8/9
Answer: C
A) b+c2
B) √bc
C) b−c2
D) None of these
Answer: A
A) 10/x
B) 100/x
C) 1000/x
D) x/10
Answer: B
A) 47
B) 48
C) 49
D) 50
Answer: B
A) 5
B) 10
C) 25
D) 100
Answer: C
A) 1/56
B) 1/48
C) 1/8
D) 3/8
Answer: A
A) 1.75
B) 3.5
C) 7
D) 8
Answer: B
A) Intersection
B) Radiation
C) Resection
D) Traversing
Answer: C
A) 25°00’
B) 95°00’
C) 148°00’
D) 190°00’
Answer: D
A) 3°
B) 87°
C) 93°
D) 273°
Answer: D
A) Bowditch’s rule
B) Transit rule
C) Empirical rule
D) None of these
Answer: B
A) 99.345 m
B) 100.345 m
C) 100.655 m
D) 101.870 m
Answer: A
A) Foresight
B) Intermediate sight
C) Backsight
D) Any sight
Answer: C
A) Collimation error
B) Error due to earth’s curvature
C) Error due to atmospheric refraction
D) All of these
Answer: D
A) Sedimentary rocks
B) Igneous rocks
C) Metamorphic rocks
D) None of these
Answer: A
A) Igneous rock
B) Sedimentary rock
C) Metamorphic rock
D) Volcanic rock
Answer: B
A) Petroleum
B) Spirit
C) Coaltar
D) Turpentine
Answer: D
A) Hard
B) Soft
C) Light
D) Heavy
Answer: A
A) Lime
B) Lime putty
C) Cement wash
D) Chalk
Answer: D
A) Enamel paint
B) Aluminum paint
C) Asbestos paint
D) Cement paint
Answer: C
A) Top face
B) Bottom face
C) Longer face
D) Shorter face
Answer: A
A) Basalt
B) Slate
C) Limestone
D) Sandstone
Answer: C
A) Strength
B) Durability
C) Workability
D) Water content
Answer: C
A) Meter
B) Square meter
C) Cubic meter
D) None of these
Answer: B
A) 0.62 kg
B) 0.89 kg
C) 1.58 kg
D) 2.35 kg
Answer: C
A) Estimation
B) Valuation
C) Pricing
D) Costing
Answer: B
A) 2,400 kg
B) 4,600 kg
C) 7,850 kg
D) 10,000 kg
Answer: C
A) B + d + Sd
B) Bd + Sd^2
C) Bxd - Sd^2
D) (Bd + Sd^2)/2
Answer: D
A) Sand
B) Silt
C) Clay
D) None of these
Answer: A
A) Sandy soil
B) Silty soil
C) Gravel soil
D) Clay soil
Answer: D
A) Moisture content
B) Permeability
C) Capillarity
D) None of these
Answer: B
A) Sands
B) Gravels
C) Clays
D) Highly organic soils
Answer: C
A) Tan (45°-θ)
B) Tan² (45°+θ)
C) Tan² (45°-θ)
D) Tan (45°+θ)
Answer: C
A) Bulldozer
B) Clam shell
C) Scraper
D) Dump truck
Answer: D
A) Event
B) Free float
C) Dummy
D) None of these
Answer: C
A) FF = EFj – ESi – D
B) FF = ESj – ESi – D
C) FF = EFi – ESi + D
D) FF = EFj – ESi + D
Answer: A
A) tE = (tO + 4tL + tP)/6
B) tE = (tO + 4tP + tL)/6
C) tE = (tO + tP + 4tL)/6
D) tE = (tP + 4tO + tL)/6
Answer: B
A) Shortest path for the earliest completion of the project
B) Longest path of the network for the earliest completion of the project
C) Ideal path for the earliest completion of the project
D) None of the above
Answer: B
A) Optimistic time
B) Pessimistic time
C) Most likely time
D) All of these
Answer: D
A) Scope
B) Resources
C) Team
D) Budget
Answer: C
A) Quality assurance
B) Quality planning
C) Quality control
D) Quality audit
Answer: A
A) Mega projects
B) Large projects
C) Medium projects
D) Small projects
Answer: D
A) Conditions of contract
B) Bill of quantities
C) Valid agreement
D) Specification
Answer: C
A) Chairperson of District Coordination Office
B) Chief District Officer
C) Chief Executive Officer
D) Chief Communication Officer
Answer: B
A) Vicarious liability
B) Negligence
C) Tort
D) None of these
Answer: A
A) Engineering
B) Law
C) Medicine
D) Teaching
Answer: D
A) Engineering values
B) Engineering conduct
C) Engineering ethics
D) Engineering principles
Answer: C
A) Ethical
B) Emotional
C) Responsible
D) Intellectual
Answer: B
A) Mediation
B) Adjudication
C) Litigation
D) All of these
Answer: D
A) Perfect competition
B) Oligopoly
C) Monopoly
D) None of these
Answer: C
A) Infinite cost
B) Life cycle cost
C) Life cost
D) Project cost
Answer: A
A) Acid test ratio
B) Liquidity ratio
C) Current ratio
D) Debt ratio
Answer: C
A) Equivalent revenue
B) Marginal revenue
C) Average revenue
D) None of these
Answer: B
A) Annuity
B) Amortization
C) Depreciation
D) Bond
Answer: A
A) Work charged establishment
B) Overhead cost
C) Supervision cost
D) Contingency
Answer: D
A) Simple interest
B) Interest
C) Rate of interest
D) Principal
Answer: B
A) (1 + i/n)
B) (1 + i/m)
C) (1 + m)
D) (1 + n)
Answer: B
A) 1/250 of the span
B) 1/300 of the span
C) 10 mm
D) 25 mm
Answer: B
A) Q = S + F
B) Q = S – F
C) Q = F – S
D) Q = F × S
Answer: D
A) d/m
B) dr/(1 + r)
C) md/(1 + m)
D) mrd/(1 + r)
Answer: B
A) Modulus of elasticity
B) Modulus of rigidity
C) Poisson’s ratio
D) Bulk modulus
Answer: C
A) 8 mm
B) 10 mm
C) 12 mm
D) 16 mm
Answer: C
A) Compressive stress
B) Shearing stress
C) Working stress
D) Tensile stress
Answer: B
A) 100°C to 120°C
B) 120°C to 140°C
C) 140°C to 160°C
D) 150°C to 170°C
Answer: C
A) Stone dust
B) Sand
C) Brick dust
D) Cement
Answer: A
A) Retaining wall
B) Breast wall
C) Parapet wall
D) None of these
Answer: B
A) Valley curve
B) Sag curve
C) Summit curve
D) None of these
Answer: C
A) Positive grade
B) Negative grade
C) Grade
D) Gradient
Answer: A
A) T = R sin Δ
B) T = R tan Δ
C) T = R sin Δ/2
D) T = R tan Δ/2
Answer: D
A) Formation width
B) Right of way
C) Carriage way
D) Roadway
Answer: B
A) Hyetograph
B) Unit hydrograph
C) Normal hydrograph
D) Crest method
Answer: B
A) Its intensity
B) Its duration
C) Its frequency
D) All of these
Answer: D
A) Well
B) Springs
C) Artesian well
D) Rain
Answer: D
A) 15 mm
B) 20 mm
C) 25 mm
D) 30 mm
Answer: C
A) Flood wall
B) River wall
C) Dyke
D) None of these
Answer: C
A) To reduce pressure
B) At low points
C) Upstream of sluice
D) All of these
Answer: D
A) Change of diameter
B) Junction
C) Bend
D) All of these
Answer: D
A) Permanent hardness
B) Temporary hardness
C) Alkalinity
D) Acidity
Answer: B